Initial Consultation & Assessment
We walk the deck and the level below, mark stains and efflorescence on the underside, then trace them back up to drains, joints and cracks, because water rarely enters directly above the stain.
Detailed Estimate & Planning
The slab is shot blasted or ground to an open profile, oil and tire rubber are removed, and moisture content is checked. Liquid membrane will not bond to a sealed or damp surface.
Expert Installation
Drains, columns, curbs, expansion joints and cracks are detailed before any field coat goes down. Coving and reinforcing fabric have to cure in place, and clamping rings are set over the membrane, before the field coats go on.
Final Walkthrough & Cleanup
Base, intermediate and wear coats go on in sequence at the specified wet film thickness, aggregate is broadcast into the wear coat, and the deck stays closed to traffic until full cure.